QAZCLINKER has set the launch date for clinker tile production
The first product is planned for 10 April 2027. The production hall is about 95% complete, and commissioning will run from December 2026 to February 2027.
11.09.2026

Construction and installation work in the production hall is planned to finish by the end of October 2026. The main auxiliary buildings (the covered raw-material store, the materials store, the staff and utility building, the checkpoint) will be ready in November and December.
In Block A, work on the kiln section is being completed: installing ducts, the vault, thermal insulation and service platforms. The next stage is the burners and fans of the gas equipment. In Block B the drying section is 90–95% ready. In Block C the clay-preparation areas are being readied, and supervised installation of the main equipment began on 10 September 2026.